Without yet identifying the cause of the departure of Unit 6 from Costa Sur that caused the second blackout on Thursday

Without yet identifying the cause of the departure of Unit 6 from Costa Sur that caused the second blackout on Thursday

The Energy Czar, Joshua Columbusanticipated that Unit 6 of the Costa Sur plant, in Guayanilla, could be synchronized again to the electrical system “at some point” this Friday, while It is still being investigated what happened in the switch yard where the “condition” that caused his abrupt departure was detected.

In an interview with WKAQ-580, Colon explained that this transmission center, where the unit’s generation comes out through 230 kilovolt (kv) lines, is under the jurisdiction of the consortium. LUMA Energy.

According to the tsar, Unit 6 was generating about 340 megawatts (MW) when its protection system detected a “condition” in that switch yard and took it out of service at 8:26 pm on Thursday.

The event caused a second blackout that, at its peak, affected over 190,000 subscribers.

The official indicated that, as soon as the unit left, technical personnel from the two private companies in charge of the electrical system were dispatched: Generate PRresponsible for the operation of the plant, and LUMA Energy, operator of the transmission and distribution network.