The Aqueduct and Sewer Authority (AAA) hopes to complete this Friday the repair of the fault identified in a 48-inch line, in Bayamonwhich delayed the recovery of the drinking water service for thousands of subscribers in Guaynabo, Caguas, Gurabo, Saint Lawrence, Good Waters and Reeds.
In an interview with Radio Isla 1320 AM, the executive president of the public corporation, Luis Gonzalez Delgadoexplained that the break occurred at a junction between a curve and a change in direction of the tube, where the staff identified a crack.
“Our expectation is to complete these repairs today. We hope later today to open the system so that it gradually begins to fill with water and, once it reaches our pumping station and reaches the operating stations, that the pumps begin to operate”indicated Gonzalez Delgado.
The break identified on Wednesday occurred in an interconnection with the Superaqueduct, which sends water to the Finca Rosso 2 pumping plant and which is distributed to Guaynabo, Caguas, Gurabo, San Lorenzo, Aguas Buenas and Juncos.
“During the night of Thursday and this morning, the staff was working with that pipeline to ensure that it can be repaired and put it back into operation,” said the official.
The breakdown caused a new delay in the recovery of service for nearly 27,000 AAA subscribers, after the public corporation attended to three consecutive breaks discovered in a section of the Superaqueduct, also in Bayamon.
Last Sunday, AAA had reported that the work related to those three breakdowns would be completed by Monday, although the restoration of service would occur gradually, starting with the customers closest to the system and located in low-lying areas.
However, on Wednesday, while the recovery process was still continuing, AAA identified the new break in the 48-inch line. At that time, the corporation reported that 36,566 subscribers remained without service.
1 / 42 | In images: this is how the new repair of the Superaqueduct takes place. Sectors of San Juan, Bayamon, Guaynabo, Loiza, Caguas, Gurabo, Juncos and Aguas Buenas could experience from intermittencies to interruptions in the drinking water service during the repair work of three breakdowns in a 72-inch diameter line of the Superaqueduct. – Carlos Rivera Giusti/Staff
Gonzalez Delgado described recent events as part of “a streak of breaks” in the AAA’s infrastructure, although he maintained that it is not a scenario that the corporation has not seen before.
The executive president also spoke about the Total Commission held this week in the Senate, to which he appeared to answer questions from legislators about the crisis in the drinking water service.
“I can summarize it as an event in which we were able to bring information, in which we answered several of the questions that the senators had, with a series of requests for information”said.
Regarding the Stabilization Committee created as a result of the lawsuit presented by the municipality of San Juan before the courts, Gonzalez Delgado assured that there has been constant communication between the representatives involved.
“From what I have been able to see of the interaction between the two representatives, there has been constant fluid communication. They have been exchanging impressions in terms of operations and in terms of the analysis of how the system behaves,” he stated.
The official maintained that daily recommendations are issued, but insisted that the permanent solution does not consist of manipulating valves, but rather increasing the amount of water available in the system.
“Here the permanent solution is not to manipulate valves. Here the permanent solution is to bring more water into the system”said.
Gonzalez Delgado added that, while working with the available water, the AAA carries out daily operations to move the resource from one place to another and ensure that more clients can receive the service.
When asked about the possibility of reinforcing the pipeline teams, the executive president indicated that the AAA maintains a policy to attract more personnel to the public corporation.
As part of that effort, he mentioned the approval, together with the Fiscal Supervision Board, of a classification and remuneration plan.
“The classification and remuneration plan is an increase and, once we enter into collective bargaining, we can talk about better salaries,” he said.