Cogenerator unit #2 AESin Guayamawas forced out of service this Wednesday morning, limiting the level of energy reserve for the second consecutive day and increasing the possibility of selective blackouts at night.
As a result of the forced departure, more than 170,000 subscribers were temporarily without service, according to a spokesperson for LUMA Energy.
“The technical staff of AES Puerto Rico has just informed us that they had a breakdown in unit #2, which went out of service at 11:31 am The operators LUMA Energy and Generate PR They are addressing the situation to normalize operations and restore service to affected customers as soon as possible. We ask customers to be cautious in their energy consumption during peak demand hours. “This will help reduce the possibility of affecting service to customers.”expressed, meanwhile, the Energy Czar, Joshua Columbuson social networks.
With the departure of unit #2, the cogenerator leaves an electrical production deficiency of just over 500 megawatts (MW), since on Tuesday it had already suffered a breakdown in unit #1. Both units of the plant have the capacity to generate up to 254 MW.
At the time of publication, The New Day I was waiting for an expression from AES.
At 12:30 pm on Wednesday, LUMA forecast a peak consumption of 2,863 MW at night, which would leave an approximate reserve of 117 MWfar from the 700 MW with which, ordinarily, the network must be able to operate.
On Tuesday, after the breakdown in AES unit #1, LUMA reported that the implementation of load relays was “highly probable,” given a projected deficit of more than 100 MW. In the afternoon, however, Genera PR returned unit #2 of the Aguirre plant to service (Salinas) – which had been off since last week – avoiding blackouts due to lack of generation.
Early Wednesday afternoon, Aguirre #2 was producing 278 MW.
Stay connected to elnuevodia.com for the expansion of this story.