Concerned mayors associated with the slowness in reconstruction and the effects of inflation

Concerned mayors associated with the slowness in reconstruction and the effects of inflation

Reconstruction projects that have not yet been completed in the areas of education and energy, the proliferation of empty auctions and the allocation of funds from the Federal Emergency Management Agency (FEMA) that do not take into account the effects inflation are the main concerns of the members of the Association of Mayors.

The group of municipal executives of the Popular Democratic Party (PPD) met on Friday to establish their three priorities for the new year. In this regard, the mayor of Villalba and president of the organization, Luis Javier Hernandez Ortiz, detailed on Monday The new day that “the issue of post-hurricane reconstruction and the fight against bureaucracy is the main objective.”

“Excessive bureaucracy has stopped projects in all municipalities, it is a general situation. Added to this is the increase in costs and problems when awarding auctions. Processes must be simplified if we want projects to be carried out in an orderly manner. In fact, inflation has raised costs by 30% or 40% and, in some cases, the cost of projects has doubled“warned the mayor.

Hernandez Ortiz mentioned that “the biggest concern that colleagues have is that the reconstruction of the most important areas – in terms of education, energy – is very slow by the government.”

Regarding this aspect, he specified that “many of the mayors” raised concerns regarding the slowness in terms of rebuilding schools, especially those in the southern zone, which were most affected by the earthquakes that hit the country in 2020.

They cry out to simplify processes

The mayor of Villalba stated that now the problem is not resources or the advance of funds, but rather “is to find a way to simplify the processes, especially those of auctions and purchases, because we are seeing many auctions without participants or auctions with only one or two participants.”

For this reason, he indicated that he will go to Washington DC this week to hold meetings with FEMA senior management to discuss possible solutions. In these meetings, he anticipated, the director of the Central Office of Recovery, Reconstruction and Resilience (COR3) will participate, Manuel Laboywho was not available for an interview this Monday.

“I am going to propose how we can simplify the processes without duplicating efforts. There are federal processes that are less rigorous than state ones. What I am suggesting is that we comply with the federal process, instead of the state, so that, then, we can streamline the purchasing process“explained the mayor.

Hernandez Ortiz announced that another of the concerns that he will present to FEMA is that inflation is not contemplated in many of the fund allocations for the projects. “We have been fighting that fight for a long time. Uniformity in the review processes,” he noted.

As an example, he said that The reconstruction and rehabilitation of a bridge in his town costs him four times more than what FEMA allocated due to inflationand the only remedy they have to appeal is to request a review, which, he emphasized, “takes time.”

Works promoted by accelerated mechanism

Through the mechanism called Faast (FEMA Accelerated Awards Strategy), all the permanent work of the Electric Power Authority (PREPA), the Aqueduct and Sewer Authority (AAA), the Department of Education (DE) and the Housing Administration is carried out. Public (AVP).

Faast allows estimating fixed costs for projects based on a sampling of damages. It was the product of a mandate from the United States Congress and establishes that what was damaged or destroyed by Hurricane Maria will not be repaired, but will be brought to the industry standard level.

Faast began in 2020, but each benefited government agency was integrated in different years, and had to submit a work plan to FEMA. Reconstruction projects have performance periods, according to rules established by FEMA. In general terms, the deadline for the execution of the permanent work was last September, but the government of Puerto Rico requested an extension, which was granted, in principle, for a few months and then until September 2025.

However, regarding the projects covered under Faast, the government of Puerto Rico is committed to requesting extensions from the federal government to complete the works.

According to data provided by the COR3 website, there are $15.7 billion in funds obligated by FEMA for work under Faast. Of that amount, $9.5 billion are for PREPA projects, $2.1 billion were assigned to the DE, $3.7 billion to the AAA and $554.3 million to the AVP.

Of a total of 784 projects already submitted to FEMA, only 115 have been completed, for $127,310,040, and another 259 are “in progress,” for $1,326,749,675, according to COR3. In the case of the DE, there are only 10 of 174 projects completed, for $4,713,787. The PREPA, of 239 projects, shows 23 completed, for $88,868,338.