In a “great victory” for the environmental fight, the Court of First Instance of Aguadilla revoked the permits that gave way to the construction of the Cyclist and Pedestrian Walk of Cornerwhile ordering the immediate stoppage of all work related to the controversial project.
“This is something very big, we want this victory to be for the people of Puerto Rico, and it is a resounding victory for the people, for the communities, for everyone”said the environmental activist Hector “Tito” Varelaspokesperson for the Collective in Defense of the Tres Palmas Marine Reserve.
In a decision issued Thursday afternoon, the top judge Johnny Reyes resolved in favor of Ramon Diaz Zambrana and Leanne Arcuriof the organization Friends of Tres Palmasby determining that the proposed bicycle ride was authorized and processed in a manner contrary to the applicable regulations.
According to the ruling, the Highway and Transportation Authority (ACT) made substantial changes to the project without processing required amendments, used incorrect or incomplete information on environmental and location aspects, and obtained permits and certifications that did not comply with legal requirements or applicable environmental restrictions.
The superior judge also noted that “ACT has been reckless during the processing of this case.”
“The ACT continued to defend the validity of determinations and permits obtained through incorrect information even when this arose from the administrative file itself and documents related to the project.. As a result, the plaintiff had to incur expenses, preparation of documentary evidence, presentation of expert evidence and appearances. Therefore, the sum of $15,000.00 is awarded for attorneys’ fees,” the ruling reads.
Sentence on bike lane in Rincon by El Nuevo Dia
On the other hand, it concluded that the project impacted protected areas of high ecological value, including sectors close to the terrestrial maritime zone and public domain assets.
The Court revoked the Environmental Compliance Determination by Categorical Exclusion and the Single Incidental Permit of the initiative. In addition, it gave the ACT 30 days to present a plan that identifies the impacted areas and establishes measures for their stabilization and repair.
The New Day requested and watered down by comments from the ACT.
“This is a call to the Puerto Rican people that we must carry out the fight, we must carry out the demonstrations, we must be present in all these processes, both in the Legislature, in the mayor’s office, Municipal Legislature, in the communities, in the streetsin front of the authorities when we understand that they are not carrying out their ministerial work. “This is a great victory,” added Varela, meanwhile, via telephone.
Stay connected to elnuevodia.com for the expansion of this story.