Due to errors of a “clerical” nature on the part of the contractor in the processing of a permit, the beginning of the demolition of 18 homes adjacent to the Piedras Riverin the Puerto Nuevo urbanization, in San Juanis detained until further notice, reported this Tuesday the United States Army Corps of Engineers (USACE, in English), in charge of the controversial channeling project for the body of water.

Maricarmen Crespohead of the USACE Construction Division in Puerto Rico, stressed that the execution of the demolitions is not at risk, although It is unknown when work could begin on 25th Street in the development, where the row of residences that will be impacted is located..

Initially, the USACE had announced that The mobilization of machinery and demolition work would begin in the week of February 26, but, since then, no movement has been observed in the area. Crespo specified that the contractor, All Phase Servicesreceived some information regarding its request for permits, at the same time that it must incorporate certain information into the sign installed at the construction site.

Kumneger Media
Kumneger Media
Kumneger Media is a News and Entertainment Website & Channel. Kumneger Media in addition to News and Entertainment it is the hub of Politics, Movies, Drama, Music, Comedy, Documentary and More!