Six years after the passing of Hurricane Mariathe government has directed 8,102 infrastructure projects related to the disasters caused by the cyclone and earthquakes that affected the country at the beginning of 2020, a figure that represents 33% of the 24,000 projects estimated between both emergencies.
As of December 2020, before the administration of Pedro Pierluisi took control of the government, there were only 500 projects underway, indicated the executive director of the Central Office of Recovery, Reconstruction and Resilience (COR3, in English), Manuel Laboy. “By 2024, the goal is to exceed 4,000 projects and the development of critical energy projects,” anticipated the head of the agency.
Laboy’s expressions emerged during a round table, in which the “advances” that have emerged in the country’s recovery process in 2023 were presented, as well as the challenges they continue to face to lighten the work and administrative measures they have implemented, and which have resulted in more flexibility in claims and the disbursement of funds.
“When we compare 2022 with 2023, the increase in projects underway or in execution is 41%. If I go into more detail, in that comparison from 2022 to 2023, projects that were already being designed, that construction plans were being made, increased by 57%,” the official explained.
Recruitment of labor continues to be a challenge, which is why he stated that efforts will continue to offer training in the construction area and bring in foreign workers to help speed up the work. “We must continue executing with urgency, we must continue giving results, but doing so in compliance and in total transparency, that is the mission we have”he alleged.
The governor has mentioned that the reconstruction of the country will take an additional six to seven years. “At the rate we are going, between 1,000 and 2,000 projects will be completed every year,” said Laboy.
The problem of credibility with the federal government is overcome, he stated.
Energy sector: 150 approved projects
On the topic of energy, Laboy highlighted that there are 150 projects approved for construction that total $3.4 billion. Among these, he mentioned the repairs to the Aguirre Central, in Salinas, at a cost of $21 million, and to the Sabana Llanas substation, in Carolina, for $10 million. Likewise, he referred to the program for the replacement and repair of poles and luminaires, which is being carried out at a cost of $451 million.
Regarding the drinking water service, he mentioned the construction of the regional sanitary plant of the Water and sewage Authority (AAA), in Guayama, at a cost of $93 million; and the beginning of dredging work in the Carraizo reservoir, for $88 million. The reconstruction of a sanitation plant in Humacao is also underway, a project for which $12 million has been allocated.
At the municipal level, he highlighted the construction of a hospital on the island municipality of Vieques, a project that is being developed at a cost of $85 million, as well as the Felix Millan stadium in Yabucoa, for $26 million.
Likewise, he highlighted the rehabilitation of ResiCampus, one of the two main housing centers for students in the Rio Piedras Campus of the University of Puerto Rico (UPR), which has remained closed since 2020, and the reconstruction of the Cardiovascular Center of Puerto Rico and the Caribbeanat the Medical Center, at a cost of $40 million.
Among the completed projects is the bridge in the Canabon de Barranquitas neighborhood, after an investment of $4 million; the Abrahonda community bridge, in San Sebastian, at a cost of $6 million; and health care center COSSMAin San Lorenzo, for whose reconstruction $6 million was spent
Disbursements flow
Laboy reported that they hope to close 2023 with the disbursement of $2,000 million, while, for 2024, the projections are to reach $2,500 million. In 2022, funds of $1.4 billion were provided.
“Right now, they are running, between advances and reimbursements, almost $250 million that we are going to be able to disburse before December 31, achieving the goal of $2,000 million that we established for 2023. “It is the highest amount of money disbursed, mainly for permanent work,” he explained.
The municipality of Jayuya, he said, is the largest recipient of disbursements, with $41.7 million, followed by the towns of Utuado ($18.4 million), Las Piedras ($15.6 million), Yauco ($13.3 million) and San Lorenzo ($12.8 million).
At the state level, the agencies with the most disbursements are the Electric Power Authority (AEE), with $548 million, as well as the Public Housing Administration ($169 million), the AAA ($100 million) and the UPR ($78.6 million).
Another area where, according to Laboy, great progress was seen during 2023, was in mitigation projects.. “When we arrived in January 2021, there were only 11 approved hazard mitigation projects. Now we are going for 184, that has been a dramatic change,” he argued.
For these 184 projects, he added, the Federal Emergency Management Agency (FEMA) has approved a budget of $2.9 billion. The amount obligated for these works, at the moment, is $478 million. Among the flagship projects in this area is the installation of solar microgrids in Vieques and Culebra.
About the recovery of Hurricane FionaLaboy said that, in a one-year period, FEMA approved more than $259 million for 748 projects. “That there are projects executed under Fiona in one year is great news, because we are doing it while we continue to move Maria and the earthquakes”he pointed out.