After almost two weeks of unstable operation, the cogenerator EcoElectric managed to synchronize its third production unit to the network, which should help normalize the energy service, burdened by selective blackouts since the passage of the Tropical Storm Ernestoin mid-August.
The company reported in written statements that on Thursday, at 3:40 p.m., LUMA Energy authorized the entry into service of unit CT#1, with the capacity to generate 180 megawatts (MW). CT#1, which operates on natural gas, had been out of service since September 1, when EcoElectrica, in Penuelas, began scheduled maintenance work on its three units.
“In this way, we completed the maintenance and repair activities of the plant, returning its availability to 100%,” the cogenerator said.
This Friday, at 10:00 am, the two gas units and the steam unit of EcoElectrica were producing, combined, 367 MW, of a maximum capacity of 540 MW.
In recent weeks, EcoElectrica’s operations were interrupted on multiple occasions due to problems identified by LUMA in the transmission networkwhich caused the consortium to ask the cogenerator to stop generation.
According to the LUMA portal, with the restoration of EcoElectrica, the generating fleet maintained an available capacity of 3,092 MW, which would leave a projected reserve of close to 117 MW to handle the peak consumption expected for today, Friday. The estimated reserve remains well below its optimal level, estimated at 700 MW.
At the moment, the cogenerator AES Puerto Ricoin Guayama, has one of its two units out due to a breakdown, and the fleet managed by GeneraPRalso, has four of eight base units shut down, resulting in a capacity close to 1,500 MW that is not available.