Energy Bureau criticizes GeneraPR after canceling three inspections of the San Juan power plant at the last minute

Energy Bureau criticizes GeneraPR after canceling three inspections of the San Juan power plant at the last minute

Just days after notifying GeneraPR which was exposed to penalties for alleged “false representations” regarding a project to purchase generation units, the Puerto Rico Energy Bureau (NEPR) again demanded that the company show cause why it should not be fined after canceling, in the last two weeks, three scheduled inspection visits that personnel from the regulatory body tried to make to the San Juan plant.

The NEPR stated, in the most recent resolution and orderthat “last-minute” cancellations “are not an isolated incident, but part of a deeply worrying pattern that reflects a systemic disdain for regulatory authority.”

“This recurring behavior is unacceptable and poses a severe threat to the integrity of the regulatory framework established to safeguard the provision of safe, reliable and affordable electric service for the people of Puerto Rico.”the entity stressed in the document issued on Friday, which was initially disclosed by the commentator Jay Fonseca.

In total, GeneraPR faces three fines of $25,000 each for the cancellations corresponding to August 19, 20, and 26, for a total of $75,000. The NEPR gave the generating fleet operator until September 5 to show cause as to why a penalty of that amount should not be imposed, which represents the daily limit that the agency can apply against electric companies.