He Puerto Rico Energy Bureau (NEPR) determined on Tuesday that the delays and increased costs of the project to acquire backup or rapid response power generation units for the power plants Jobos, Daguao and Dry Wood were the result of misrepresentations by the consortium GeneraPR.
However, the regulatory body decided not to fine the company in charge of most of the electricity generating plants previously operated by the Electric Power Authority (AEE), and only warned that if it continues to fail to comply, it will impose daily fines and possible additional sanctions..
The NEPR also ordered GeneraPR to complete the project within the agreed time frame. and achieve “commercial operation” by the end of spring 2026.
“If GeneraPR had reason to believe that the schedule and costs would increase, it was its responsibility to promptly notify us. Since GeneraPR guaranteed that it would maintain the schedule and costs and failed to promptly notify us of the alleged project cost overruns and delays, it must now fully comply with what it represented in terms of time and costs, which led to the approval of (the) reconfiguration of the NEPR project RFPs,” the agency highlighted in the seven-page resolution.
NEPR also stated that GeneraPR will be fined up to $25,000 for each day that the project is not completed beyond the established date.
“Through this resolution, the NEPR seeks to ensure clarity and accountability, while always protecting the public interest,” he added.
According to the document, GeneraPR told NEPR that its approach could reduce completion time by nine to 12 months.However, the company currently proposes a completion date of 2027.
“Therefore, in order to maintain the terms originally represented by GeneraPR, which were the basis for our approval, NEPR is ordered to complete the project and achieve (the) commercial operation date by late spring 2026in accordance with the AEE approach,” the resolution adds.
The regulatory body also acknowledged that the increase in the cost of the project would be covered by funds from the Federal Emergency Management Agency (FEMA), and that such costs will not be paid by consumers.
Similarly, the NEPR emphasized that, In the event that FEMA does not assume the additional costs incurred due to the reconfiguration of the requests for proposal, GeneraPR will be responsible for covering them.
The NEPR assured that it will continue to monitor the progress of the project and indicated that GeneraPR must continue to provide monthly reports on the status of the project, including unforeseen developments that may affect the cost or schedule.