He Puerto Rico Energy Bureau (NEPR) imposed on the Electric Power Authority (EEA), LUMA Energy and GeneraPR administrative fines of $500 for each day of delay in delivering a priority plan to address the most pressing problems of the electrical grid, an amount that is just a fraction of the $25,000 that, by law, is set as the maximum for penalties issued by the regulatory body.
PREPA, which submitted its plan on July 19, 16 days after the July 3 deadline, was fined the most, $8,000. LUMA and Genera, which faced the same deadline, were fined $3,500 and $2,500 for delays of seven and five days, respectively. On the whole, The penalties total $14,000.
The three entities must comply with the payments within a period of 20 days from the notification of the fine, which was issued on Friday.
In the case of private operators, the disbursements “must come from their fixed payment”, referring to the amounts they accrue contractually. In the current fiscal year, LUMA will receive a payment of $135 million, while Genera will receive around $24 million.
The development of the respective priority plans was ordered by the NEPR on June 13, one day after a massive blackout, associated with a breakdown in a transmission line, which at its peak left nearly 350,000 customers without servicearound a quarter of the universe of subscribers. Shortly before, catastrophic damage had also occurred to the transformer of a substation in Santa Isabel, which left families in this town, Aibonito and Coamo without service.
On July 5, two days after the 20-day deadline for public corporations and private companies to submit their plans expired – and after all of them, separately, requested extensions – NEPR denied the extensions and warned that they were exposed to fines of up to $25,000 for each day of non-compliance. and demanded that they show cause why they should not be penalized.
By submitting their preliminary plans late, all three parties asked the NEPR to waive the imposition of fines.
Among the proposals that Genera included in its priority plan, was the rental of temporary generators with a capacity of up to 565 megawattsproduction that, according to the company in charge of the generating fleet, would practically eliminate load reliefs. Meanwhile, LUMA identified 11 electrical substations whose transformers are in a “vulnerable” state.
PREPA, meanwhile, listed initiatives in its plan aimed at addressing hydroelectric plants, including multiple proposals that the NEPR has previously rejected.