Energy Bureau opens Genera PR incentive plan to public discussion

Energy Bureau opens Genera PR incentive plan to public discussion

In view of the approval of the criteria that will govern the contractual incentives of Generate PR –operator of the thermoelectric fleet of the Electric Power Authority-, he Puerto Rico Energy Bureau (NEPR) summoned the company to a technical hearing and opened a public comment period that will last until January 19.

The technical hearing, in accordance with a NEPR resolution of December 20, will be held on January 12, at 2:00 pm, in hybrid format (in-person and virtual).

“The form and content of Genera’s Fuel Optimization Plan (…) will have a direct impact on how cost savings are achieved and measured, and will directly impact Genera’s compensation under the (operating contract) and portion of the savings that will benefit consumers”stressed the NEPR.

The initial version of the fuel plan submitted by Genera PR to the NEPR, publicly disclosed in September, contemplated savings amounting to $196.3 million throughout fiscal years 2024 to 2028. In the document, the operator outlined seven savings strategies, subdivided between initiatives related to “acquisition”, “optimization” and “efficiencies” in fuel use.

Of the $196.3 million that would be saved between now and 2028, $27.3 million would be achieved this fiscal year. According to the privatization contract, half of the savings are credited to Genera PR in the form of incentives and the rest would benefit consumers in the form of reductions on the electricity bill.

In the resolution of December 20the NEPR specified that public comments on the plan must be sent by email to the address comments@jrsp.pr.gov.

Since it began operations on July 1, 2023, Genera PR awarded two of the main fuel purchase contracts. On October 31, the one-year contract for the supply of bunker C, awarded to Novum Energy Trading, for $1,170 million. Until that date, bunker C – a petroleum derivative – supplied it Puma Energy.

In the case of diesel supply, the roles were reversed, since Puma received the $452 million contract – effective as of November 17 –, which was previously in the hands of Novum.

The NEPR highlighted that, in a previous motion, Genera PR asked it to “certify” both fuel contracts under the initiatives listed in the Fuel Optimization Plan. In the resolution of December 20, the regulator asked Genera PR to specify what such action consisted of and “what the impact would be if the Bureau granted the certification request”.

According to your contract, Genera PR can earn up to $100 million annually in bonuses based on its performance under different categoriesincluding savings and other indicators, such as the availability of power plants and job security.

Genera PR receives a base compensation of $22.5 million for each year of the contract.