He Puerto Rico Energy Bureau (NEPR) rejected, this Monday, the request presented on September 16 by the consortium of LUMA Energy for a new increase of 2.9 cents per kilowatt-hour (kWh) in electric energy bills starting in October.
“After evaluating the motion presented by LUMA Energy on its merits, as well as its response to the information requirements of the NEPR, the Bureau reported that the factors of the Fuel Purchase Adjustment Clause and the Subsidy Clause prevail unaltered and in force. of Fuel, as approved by the Resolution of June 30, 2024”he maintained in written statements.
These factors will remain in effect from October 1, 2024 to December 31, 2024 or until modified by the NEPR.
In its resolution, the Bureau also warned LUMA Energy that failure to comply with this resolution will be interpreted as a violation of the entity’s orders and may result in the imposition of administrative fines of up to $25,000 per day, per violation, as well as any other administrative sanction that the agency deems necessary.
The energy consortium had presented a motion to adjust the rate, arguing that the increase would be due to the high cost of the fuel used by the company. GeneraPR for energy production.
According to LUMA, “the cost of generation fuel used by GeneraPR during the months of June, July and August was higher than expected”and a similar situation is anticipated between October and December, information that the company that manages the electrical network included in the report submitted to the NEPR for the quarterly factors of the fuel cost adjustment (FCA, in English) and the adjustment for purchase of energy in customer rates.
“These additional costs, together with the forecast for October-December, indicate an expected increase in factors of approximately 2.9 cents per kilowatt-hour (kWh) on customer bills,” the consortium noted in a press release.
In defending the request, the president and chief executive officer of LUMA, Juan Sacamaintained that the proposed increase is an effect of the increase in fuel costs and continuous generation problems. In that direction, he pointed out that “the lack of availability of larger generation units forces us to dispatch units that use diesel fuel, which is expensive.”