He Puerto Rico Energy Bureau (NEPR) ratified the approval of 11 solar photovoltaic generation projects and 11 energy storage projects, after determining that the revisions made to the contracts comply with the regulatory guidelines established by the agency in previously issued resolutions.
The action occurs after the Electric Power Authority (AEE) and “Proponent No. 3” submitted revised versions of the Power Purchase and Operation Agreements (PPOAs), in compliance with a resolution and order. In that determination, the NEPR had concluded that a previous version of the contracts contained material changes that exceeded the authorized modifications, and therefore ordered its correction before considering its final approval.
In written statements, the NEPR maintained this Saturday that the decision “reaffirms the approval of projects that, together, are part of the portfolio of initiatives promoted to increase the renewable generation and storage capacity of the electrical system, strengthen its reliability and resilience, and advance compliance with the public energy policy of Puerto Rico”.
“The contractual pricing mechanism guarantees that the portfolio remains in continuous compliance with the price limitations established by the Energy Bureau and that Puerto Rico subscribers do not assume costs that exceed those authorized,” the resolution and order establishes.
The NEPR clarified that each project was independently evaluated to ensure compliance with all applicable legal and regulatory requirements.
As part of the approval, The NEPR ordered PREPA to present semiannual reports starting in January 2027 to monitor the development of each projectmonitor any changes in the composition of the approved portfolio and ensure continued compliance with authorized cost parameters.