After remaining closed since Hurricane Fiona two years ago, the PR-861 highway, better known as “the curves,” reopened to traffic, the mayor of San Juan announced on Monday. Toa Alta, Clemente “Chito” August.
The road, which has a traffic of over 21,000 vehicles daily, had been the subject of continuous complaints by the municipal executive, who had denounced –even in a public event before Governor Pedro Pierluisi– the alleged lack of action by the central government.
“Today (Monday), I celebrate with my people the reopening of this road that is so crucial for Toa Alta,” said Agosto, in a written statement. “It is time for leaders to act like responsible adults, putting aside political divisions and focusing on the real needs of the people”, he added.
Agosto pointed out that the repair project had been paralyzed for almost a year, and that is why, faced with this situation, he protested to the first executive, at an event in which he opened his button-down shirt to show a t-shirt with a message demanding immediate action in favor of the Toalta community.
However, the CEO of the Highway and Transportation Authority (ACT), Edwin Gonzalez Montalvosaid on Monday that the project was not halted, although it was delayed, he said, because the continuous landslides on the mountain forced amendments to be made, in the middle of the work, to install nets that, in principle, were not planned.
“This landslide was probably the most complicated one we had in the ACT after Hurricane Fiona. Immediately after the event, we were inspecting. As we were doing the investigations, there were situations from previous events that had not been addressed.”assured Gonzalez Montalvo to The New Day.
The PR-861 project, which consisted of repairing landslides and collapses, was carried out at a cost that exceeded $10.7 millionmostly from the Federal Highway Administration (FHWA) and a smaller portion from the ACT.
In addition to the large landslide that completely destroyed the road during Fiona’s passage, the situation continued to worsen due to rain events. The ACT director stressed that it was a challenge to work on the lower part of the mountain, as there were large loose stones on the upper part, which could cause another landslide.
The installation of nets and anchors on the upper part raised the cost of the work, which was originally around $8 million. Gonzalez Montalvo highlighted that, for the installation and anchoring of the nets, the workers had to use the technique of rappelling.
“That took additional time and additional investment. In that project, we even transported the materials to the top of the mountain by helicopter because the continuous rains affected transportation through the mountain.”he explained.
Specifically, the project consisted of the construction of various retaining walls anchored with micropiles and soil retention and reinforcement (soil nails); the installation of modules for the retaining walls, the execution of works of scaling (climbing) and slope stabilization through the installation of 2,400 square meters of steel mesh, the construction of 300 linear meters of concrete barrier, the installation of a metal barrier, pavement scarification and application of 2,660 tons of asphalt –with a thickness of 2 inches– and the installation of traffic control and safety signs, among other details.
The project began in March 2023 and was expected to be completed in December of that year. The executive director of the ACT recognized the importance of this road for the people of Toalta and residents of neighboring municipalities, and, like the mayor, celebrated the opening.
“It is a route that provides a lot of service to citizens and can save a citizen 40 to 50 minutes (compared to alternative routes)”Gonzalez Montalvo said.
The mayor, for his part, advised citizens on the safe use of the road. “The most important thing is that our people can once again travel on this road safely. This opening is not only a victory for Toa Alta, but also a sign that the persistence and voice of our people will always prevail,” he said.