LUMA Energy He stated that the new deadlines that the Puerto Rico Energy Bureau (NEPR) granted –in response to a previous request for an extension– will not be sufficient to complete the review and submit its proposal. Integrated Resource Plan (PIR) of the electrical system, which is why it asked the regulatory body for a “confidential” meeting to explain the current status of the process.
According to LUMA, of the 11 months that have passed since it recruited the firm Black & Veatchat a cost of $3 million, to serve as its technical consultant in developing the PIR, “six have been dedicated to solving software programming problems that caused illogical results” in the scenarios modeled for the future of the power grid.
“The complexity and challenges of Puerto Rico’s electrical system and regulatory requirements, coupled with unforeseen delays associated with modeling software, make the November 29, 2024 delivery deadline impossible to meet.”the consortium stated, referring to the date set by the NEPR in an august resolution.
In that resolution, the regulatory body ordered that, by November, LUMA will deliver the possible scenarios of the electrical system for the period from 2025 to 2044and that certain analyses related to the transmission and distribution networks be submitted on or before February 28 of next year. In June – when the previous term expired – LUMA had requested that the delivery period be extended until May 16, 2025.
The NEPR had previously granted a first extension, from March 28 to June 28 of this year.
In the PIR – a document that, by law, must be reviewed every three years – the electricity system operator must produce an analysis of the generation resources that will be available for the next two decades, as well as outline the investments that will be necessary for the country to meet the consumption projected over that period.
In one of the preliminary versions of the PIR, for example, LUMA introduced the possibility that, by the end of this decade, an underwater electric cable is developed between Puerto Rico and the Dominican Republic.
According to the consortium motionfiled Sept. 11, even with delays, its work schedule remains within the 18- to 24-month time frame typically taken to develop integrated plans in “other jurisdictions with similar planning horizons.”
“LUMA and the PIR technical consultant (Black & Veatch) need time beyond November 29, 2024 to carefully evaluate the results of the software models and carefully address any illogical and impractical results for Puerto Rico.. This step and the time required to complete these reviews are necessary for LUMA to carefully and accurately develop the PIR, complete the scheduled models and tasks, and conduct meetings with stakeholders,” the transmission and distribution system operator insisted.
“LUMA proposes to schedule this confidential technical conference (with the NEPR) as soon as possible, preferably during the week of September 17-20, 2024, given the close deadlines established in the August 20 order,” LUMA added.