At the end of October, the Court of First Instance of San Juan dismissed a “mandamus” petition presented by environmental groups to stop the approval and construction of industrial renewable energy projects on land of high agricultural value.
In the appeal, submitted in August, the plaintiff groups requested that the court order the Puerto Rico Energy Bureau (NEPR) to identify suitable locations for the projects and to comply with the Land Use Plan (PUT).
But Judge Anthony Cuevas, of the Court of First Instance, stated that the “mandamus” – an extraordinary resource to force compliance with ministerial duties established by law – It is not appropriate for, among other reasons, lack of jurisdiction and because there is no unfulfilled ministerial duty.
“As this is a jurisdictional matter and a highly discretionary resource, we understand that it is appropriate to dismiss the action presented so that they can proceed with the administrative procedure before the Energy Bureau. Therefore, this Court lacks jurisdiction over the matter, since the Legislative Assembly has granted primary and exclusive jurisdiction to the Energy Bureau,” reads the ruling of last October 25.
Additionally, it establishes that “even if the Legislative Assembly had not been clear regarding jurisdiction, it would not be appropriate for us to issue the ‘mandamus’, since there is an adequate remedy in law in the administrative process that we have already established.”
The organizations sued the NEPR, the Planning Board (JP), the Office of Permit Management (OGPe), the Department of Economic Development and Commerce (DDEC) and the Commonwealth (ELA), alleging that the projects occupy land classified as “Special Agricultural Reserve” and “Specially Protected Rural Land” which, according to the PUT, must be protected.
For his part, the president of the JP, Julio Lassus Ruiz, said on Thursday that the court’s determination is “fundamental to continue executing the government’s public energy policy.”
In written statements, he indicated that “the plaintiffs tried to stop the priority and urgent issue of continuing with the development of public energy policy that impacts all citizens and the economic development of the island.”. To have a development that responds to current social, economic and infrastructure needs, it is necessary to continue executing the legislated public energy policy, which will benefit our environment.”
The plaintiff entities were Boricua Organization of Eco-Organic Agriculture, Frente Unidos Pro-Defensa del Valle de Lajas Inc., Environmental Dialogue Committee, Williamsburg Bridge (Latin Link on Climate Change), Sierra Club Puerto Rico and League of Cities of Puerto Rico .
Negative consequence for the island
“The effect (of the ruling) is very detrimental to the country, because what it does is, in this case, block people’s access to a forum. The Bureau alleges that it does not have the power or expertise to address whether or not the projects should be located in the country’s special agricultural reserve. However, what the court does is dismiss the claim because it understands that the Bureau is the entity that has the expertise and exclusive jurisdiction to address this matter.“said Omar Saade Yordan, the plaintiffs’ lawyer.
In an argumentative hearing in October, the groups argued that the NEPR has a ministerial duty to assess land suitable for industrial renewable energy projects. The Bureau, meanwhile, responded that it is not its responsibility to ensure that the soils are “suitable” for the installation of the works.
“For us, it took us a little by surprise (the determination). It was not something that from the argumentative hearing we could have addressed in one way or another, because there were no signs within the hearing that those were going to be the possible responses from the judge. We feel a little disappointed,” declared Marissa Reyes, from the Boricua Organization of Eco-Organic Agriculture.
The entities, Saade Yordan said, will request a reconsideration.