:format(jpeg):focal(4515x2995:4525x2985)/cloudfront-us-east-1.images.arcpublishing.com/gfrmedia/AKTVVMWYWRGQFH3F3U2XGKIP6I.jpg)
Judge Abid Quinonesof the Aguadilla Court, warned the intervening parties in the controversy over the wall erected in front of the Sol y Playa condominium, in Rincon, that the hearing held today, Wednesday, would not conclude until the plan to demolish the illegally carried out work was defined. .
“This must be resolved today”ruled the magistrate, who criticized the parties for the delay in completing the processes aimed at the demolition of the portion of the wall that the condominium built, in 2021, in the maritime-terrestrial area.
The superior judge noted that, three weeks after the last hearing, the Department of Natural and Environmental Resources (DRNA) had not yet issued the required authorization for the Council of Sun and Beach Owners to proceed with the demolition work. DRNA lawyer, Mildred Sotomayor, argued that the condominium representatives have not yet met key requirements for authorization, such as the delivery of mitigation and restoration plans for the coastal area affected by the construction of the wall.
For her part, the lawyer of the Council of Owners, Amy Ruiz Goyco, argued that the DRNA was demanding additional requirements to those stipulated in the agency’s Regulation 4860, which regulates the management of the maritime-terrestrial zone. Faced with this approach, Sotomayor replied that the process is governed by the orders issued by the court and not by the ordinary procedure, since the condominium began construction illegally.
“This already borders on the absurd. “We continue to drag our feet on the matter.”Quinones exclaimed, emphasizing that today marks 13 days since the meeting that the DRNA held with members of Camp Carey, an environmental group that presented a proposal to take charge of the demolition. The judge also scolded the Planning Board for not attending the meeting with the organization, to which the agency’s attorney, Alfonso Oronaresponded that the expertise in matters of environmental permits falls to the DRNA.
They reject offer from environmental organization
Before Quinones declared a half-hour recess at around 10:40 am, Ruiz Goyco indicated that the Council of Owners had reached an agreement with the engineer Emilio Colon Zavala –who was present in the room– to take charge of the demolition works. The legal representative of the condominium specified that, since September 6, the company of the former president of the Builders Association completed the procedures to obtain an insurance policy and that it would remain to obtain the payment of the deposit to present all the documentation to the DRNA, with a view to to obtain a demolition permit.
Asked by Quinones about how much time the parties would need to agree on a start date, estimated time for completion of the demolition and terms for a mitigation and restoration plan, Orona indicated it would be a matter of minutes. “It’s going through the ‘checklist’”said the lawyer.