This Wednesday, a judge ordered the demolition of some illegal structures on the Camino del Indio, Las Mareas sector, in the Bahia de Jobos Reserve, in Salinas, the Department of Natural and Environmental Resources (DRNA) reported in a press release.
The order establishes that the structures do not have construction permits, they explained, in written statements by the DRNA secretary, Anais Rodriguez Vega and mayor Karylin Bonilla.
Judge Josian J. Rivera Torres, of the Court of First Instance of Guayama, also revoked by ruling the use permit for having been issued without jurisdiction and endorsements, and consequently it is null and void ab initio.
“The recent court decision reaffirms the unwavering commitment of this Administration to the protection and conservation of the environment and natural resources of Puerto Rico. It is time for those who think they are above the law to understand that public property is a shared heritage, not a private property. Actions that threaten this legacy have no place on our Island. Our responsibility is to guarantee its respect and care,” said the head of the environmental agencies.
For her part, the mayor pointed out that “the Court’s determination was as expected and helps citizens keep in mind the importance of compliance with laws and regulations. We in the Municipality of Salinas continue to work actively to protect the natural resources that belong to us all.”
The court gave co-defendant Miguel A. Flores Torres a period of 30 days to comply with the Demolition Order, which will be under the supervision and approval of the DRNA. If it does not comply with it within the established time, the Municipality of Salinas has the authority to carry out the demolition, with the condition that Flores covers the expenses incurred.
On September 7, 2023, the DRNA and this municipality presented a declaratory judgment and statutory injunction under Article 14.1 of Law No. 161 of December 1, 2009 (Act to Reform Permit Processes in Puerto Rico) against engineer Angel Rodriguez Sanchez and Flores Torres.
The plaintiffs contended that the Planning Board concluded in a prior administrative proceeding, the determination of which is final and final, that Use Permit 2019-279203-PUS-06518 was issued without jurisdiction by Rodriguez as a Licensed Professional, whose Accreditation Certification is expired since October 2017, and in violation of the Joint Permit Regulations of 2020. Rodriguez issued the permit in 2019.
The defendant will have to demolish – on an estimated property of 507 square meters – a structure under construction in block and concrete; a small finished structure; fences; construction materials in the area and stairs and even a dock.
In addition, a galvanized steel access gate and chain-link fence with concrete footing and a concrete fence on the east side and chain-link fence on the west side. The length of the identified fences is as follows: rear, 16 meters; right side, 33.5 meters, left side, 33.5 meters; front, 16 meters.
The entire property of land where the illegal construction is located is located in an area delimited as a Coastal Barrier (CBRS – Coastal Barrier Resource System). The Coastal Barrier constitutes a declaration by the Federal Government not to participate and reject the development of said areas.
In addition, 98% of the land is located in the PR district. The PR (Resource Preservation) District comprises properties or parts thereof whose existing natural order must be maintained to a maximum. No construction is allowed in said district, except those related to scientific studies.
Likewise, this property is part of the Jobos Bay National Estuarine Research Reserve, under federal and state administration and regulation.
Flores Torres is also sued, along with a dozen other people, in another separate legal action by the DRNA, for invading and appropriating those public lands.