For the fourth consecutive day, tens of thousands of subscribers LUMA Energy were left without electricity earlier than the usual peak hour due to load shifting caused by a generation deficitconfirmed Hugo Sorrentinispokesperson for the consortium.
Although the peak demand time is between 6:00 p.m. and 9:00 p.m., Sorrentini said the first change was recorded at 3:55 pm, when the consortium’s website showed that about 40,000 subscribers were without electricity.
The spokesman said that of that number, more than 35,000 customers were without power due to selective blackouts.
As of 4:15 p.m., LUMA Energy’s service status portal showed a decrease in the number of customers without service. According to the website, 12,842 customers remained without power, mostly in the Bayamon (over 8,000), Carolina (over 1,000), Mayaguez (792), Ponce (784) and Caguas (674).
On Saturday afternoon, the consortium reported that a breakdown in a transmission line in Bayamon had impacted the electricity service in that region.
At that time, Sorrentini explained that, during a helicopter patrol, a point was identified, in a wooded area, where vegetation impacted the transmission line, so it is understood that the breakdown occurred in the aforementioned place.
However, he confirmed that the line was repaired on Saturday afternoon.
For its part, GeneraPR reported on Friday that unit 6 of the Costa Sur Power Plant suffered a failure due to loss of vacuum, which caused it to go out of service. The consortium explained that vacuum is crucial in the condensation process of the steam that has passed through the turbines.
“This vacuum is necessary to maximize the efficiency of the system, as it facilitates the conversion of steam into water, which can then be recirculated and reused in the electricity generation process,” the consortium added on social media X.
The New Day tried to contact GeneraPR to find out the status of the work on the damaged units, but has not yet received a response.