The legal representation of LUMA Energy requested the Court of Appeals to remove from the judicial record the brief presented by the Puerto Rico Energy Bureau (NEPR) in opposition to the review appeal presented by the consortium, due to changes in its performance metrics.
Said elimination would have the consequence that the panel of judges in charge of the case would then have to resolve the controversy without taking into account that document, which, in addition, has new determinations that were not in an original resolution of the Bureau, LUMA said.
“From the record there are no grounds to exempt the NEPR from faithful compliance with the regulatory requirements related to the presentation of documents within the terms granted for this and that extension requests are filed in a timely manner and for just cause,” LUMA pointed out, stating that the NEPR did not comply with Rules 63(A) and 72(B) of the Court, so it would be appropriate not to consider the brief received after the deadline.
Given that the NEPR is an administrative agency with quasi-judicial functions, LUMA Energy went directly to the Court of Appeals in mid-July to demand a review of the performance metrics approved by the Bureau, a body that modified the consortium’s proposals in a way that The electricity grid operator considered it “capricious” and that, supposedly, it undermines its possibilities of earning the economic incentives – almost half of them – provided for in the privatization contract.
In its response submitted to the intermediate forum, the NEPR stressed that, in the evidentiary hearings it organized, in February 2023, LUMA officials themselves recognized the need to adjust the eligibility parameters for the incentiveswhen considering the time that had passed since the company had submitted its proposal and the possibility that – as has happened – the entry into force of the bonuses would be delayed due to the prolongation of the financial restructuring process of the company. Electric Power Authority (AEE).
In the motion that LUMA filed on Friday, it noted that the Bureau presented within the deadline – after two extensions – its arguments opposing the appeal for review of the administrative decision presented by the group Local Environmental and Civil Organizations (LECO) in the same case, “but not so with respect to LUMA’s appeal.”
“It was not until September 27, 2024 that the NEPR presented its Allegation in Opposition to the Appeal for Judicial Review presented by LUMA. Namely, one week after the deadline of September 20, 2024 granted by this Honorable Court. In NEPR, however, it did not include in its Allegation or in the Motion of Excess, an explanation for the delay of one week in presenting its Allegation,” LUMA pointed out.
The private consortium maintained that the record of the case does not provide justification, much less just cause, for the alleged non-compliance by the NEPR or for the late presentation of its argument. The New Day requested a reaction from the NEPR on this matter, but at the time of going to press there was no response.
LUMA also argued that the Supreme Court ruled in a 1975 case that “the rule is that administrative agencies do not have standing to become parties when they have acted in their quasi-judicial capacity.” In that direction, he maintained that “(…) in at least four instances in its late argument, the NEPR itself acknowledged that it does not appear as a party in this case but rather as the independent and expert entity in charge of issuing the final determination on the performance incentive mechanisms. proposed by LUMA”.
Referring to what the Supreme Court of Puerto Rico has resolved, LUMA defended that since there is a controversy regarding the correctness of an adjudicative decision and whether the adjudicator satisfied the basic guarantees of due process of law, “said appealed agency “It is not entitled to appear in defense of its ruling and adjudicative process.”