The LUMA Energy consortium would begin, in 2024, a project to replace the almost 1.5 million meters that measure the consumption of its clients, with the objective of installing, in three years, intelligent equipment that provides real-time visibility of consumers affected by breakdowns.
The project is conditional on the approval of funds, in the coming months, by the Federal Emergency Management Agency (FEMA).
The replacement of the meters is part of LUMA’s five-year plan, its president, Juan Saca, announced today, Wednesday, and Its goal is to reduce the frequency of service interruptions by 75%.
“We think we can start this project sometime in 2024. Those 1.5 million meters and other technological devices that we are going to implement in three years will allow us to understand what is happening and if someone is having a problem at home. (we can identify it). Today, (the affected subscriber) has to call us, because from the (electrical distribution) substation to the customer we do not have any visibility,” Saca said at a press conference.
LUMA’s main regulatory officer, Mario Hurtado, reported, for his part, that the estimated cost of installing smart meters is estimated at $875 million, and specified that the Puerto Rico Energy Bureau gave, in recent months, its endorsement of the formulation of the project, which is currently submitted to FEMA.
Funding will ultimately depend on FEMA determinations, but Hurtado anticipated that The money will come from a pool that will combine funds authorized under both sections 406 and 428 of the federal Stafford Act.
Under section 428, FEMA approved $9.5 billion to rebuild Puerto Rico’s electrical grid, while section 406 provides additional funds for hazard mitigation projects.
Saca explained that the project “will allow us to do other wonderful things. For example, if a person in your home has a health problem and needs some type of medical care, such as dialysis, this will eventually allow us to prioritize exactly how we are going to respond to an emergency.”
“We will have a more accurate measurement of consumption and, potentially, we will be able to offer differentiated rates so that consumers can decide, if practical, how much and when they consume (energy) so that the bill is not a surprise,” he said.
In the past, LUMA has stated that the numbers of customers without service that it publicly discloses are estimated based on identified breakdowns. The consortium used this argument to justify, a few months ago, its request to the Power Outage portal – which collects data on interruptions in US jurisdictions – to remove the statistics corresponding to Puerto Rico.
Five year plan
According to the president, before achieving a 75% reduction in interruptions within five years, LUMA aspires to a 50% reduction in the next two years.
At the time of this publication, the consortium had not shared with The new day your current SAIFI and SAIDI metrics, the indicators used in the industry to calculate the average frequency and duration of interruptionsrespectively.
Yesterday, Tuesday, Saca and the vice president of Engineering, Assets and Capital Programs of LUMA, Shay Bahramirad, announced that a vegetation clearing project on transmission and distribution lines will begin later this year, spanning about 16,000 miles through 2026. According to the consortium, more than half of the service outages relate to the lack of control of the vegetation.
The executive anticipated that, next year, some 5,000 modern technology devices will be installed on the lines, which will make it possible to identify and anticipate breakdowns due to different causes, as well as speed up the restoration of service. After five years, LUMA will have installed 35,000 of these devices, Saca assured.
“70% of interruptions are temporary. It is an animal that made contact or a branch that fell on the system, but today we do not have the ability to know what happened and we have to send a brigade to check. “This automation will allow us to resolve much faster,” he said, stressing that replacing “old equipment” is key to reducing outages, along with vegetation management.
In his review of LUMA’s plans, Saca noted that 300,000 light fixtures and more than 100,000 “poles and structures” will be replaced.
In the case of the 432 electrical substations, more than 300 will be included in at least one federal project, and 17 of them will be “completely rebuilt.” Since last November, reconstruction work has begun in 12 substations: Manati, Conquistador, Aguirre, Guanica, Sabana Llana, Monacillos, Venezuela, Mora, Bayamon, Anasco, Vieques and Culebra.