After LUMA Energyin its most recent quarterly report, will report levels of service interruptions close to those recorded under the Electric Power Authority (AEE)the consortium’s chief regulatory officer, Mario Hurtadoargued this Wednesday that “advances” are not reflected in a “linear” manner and that, in the coming months, they anticipate the implementation of measures that would improve the reliability of the system.
Hurtado, who did not allude to specific factors that may have caused the increase in the duration and frequency of the blackouts in the second half of 2023, he noted that the start of the vegetation clearing program – which LUMA now projects for April or May of this year – and the installation of “automated devices” on electrical distribution lines will contribute to reversing the trend.
“We recognize the importance of improving system reliability for the customer. It is one of the main goals. We have been making significant progress in several areas to achieve, precisely, that reliability in the system and we have been able to have some important achievements. But these advances, this process, are not linear, and we are quite excited that, in the next six months, we are going to have more improvements“Hurtado stated.
For months, LUMA has pointed to the massive project to clear vegetation in the rights of way of power lines as the main bet to mitigate interruptions of electrical service. LUMA has attributed more than half of the country’s blackouts to vegetation interference with transmission lines and, to a lesser extent, distribution lines.
In the report delivered to Puerto Rico Energy Bureau On Monday, the consortium indicated that, throughout 2023, the average customer suffered 1,341 minutes of interruptions, a figure almost identical to the 1,340 minutes that were recorded in the 2020-2021 fiscal year, the last in which PREPA operated the transmission and electrical distribution. By the end of the 2022-2023 fiscal year, the so-called SAIDI (indicator on the duration of interruptions) had been reduced to 1,218 minutes, therefore, In six months, an increase of 10% was recorded.
The frequency of electrical breakdowns (SAIFI), meanwhile, increased to 7.8 per year per consumer, despite the fact that, as of March of last year, it had dropped to 6.7, a difference of 17%. In 2020-2021, the SAIFI closed with 8.0.
Initially, LUMA hoped that the clearance project, valued at nearly $1.2 billion financed by the Federal Emergency Management Agency (FEMA, in English) under its mitigation program, will start during the first months of this year, but Hurtado mentioned that it will be delayed until April or May.
He specified that, between February and March, contracts with the companies that will be in charge of the clearance must materialize, a concept that differs from traditional detachment by involving the felling of the vegetation under the wiring, instead of pruning. The magnitude of the project – which would last at least three years – has raised alarm among environmentalist sectors who have questioned whether mechanisms will exist to avoid a major impact on flora and fauna.
“There will be a period of mobilization of those contractors, and we continue in the steps with FEMA, which are important and are part of compliance with all federal rules. Yes it takes time. We are all focused and we have worked very closely with FEMA to see where we can speed things up, where we can work faster and better and where we can give advance information, and that has helped a lot. But we are talking about requirements that cannot be ignored or cut too much,” Hurtado said.
On the other hand, he pointed out that LUMA has installed 3,500 automated equipment in the distribution networks which, among other benefits, contribute to shortening interruption periods by identifying, without the need for a visual inspection, if a fault that causes the system’s self-protection responds to a temporary event. When there is no danger, the executive said, the teams “close” the lines again and resume service.
By the end of 2024, LUMA expects to have installed 5,000 devices in total, Hurtado estimated.
“Much of the time we are focusing on the fact that, if we know that something is going to fail, we take care of it before it fails.”. “We are using thermal imaging cameras to find points that are outside the limit and that, basically, can burn out, in terms of the driver and other components, and it helps us address them before they fail,” he said.