Two days after the country felt the main effects of the Tropical Storm Ernesto, LUMA Energy There is no preliminary estimate of the costs of repairing the damage to the electrical system, although the president of the consortium, Juan Sacasaid they have an “official” goal of restoring service to 90% of subscribers by Sunday.
Saca, in a press conference held at the LUMA headquarters in Santurce, said, however, that his hope is that, on Friday night, that threshold will be surpassed, which would be approached if the transmission line 36800 between Carolina and Canovanas is put into service. That line went out of service due to an incident – of still unknown cause – that left 70,000 customers without electricity in the northeast region and has even delayed restoration in the municipal islands of Vieques and Culebra.
“The goal is to pass 90% by tonight (Friday), but, to be conservative, the official statement we are making is that it will happen by Sunday morning. The truth is that we are in the process of very rapid recovery, and we want the number to be much higher,” said Saca.
As of 12:40 pm, LUMA reported that it had 82.9% of subscribers in service, which meant that 251,166 customers remained without electricityHalf of the customers without service were located in the Carolina region, impacted by the shutdown of line 36800. Saca said that, if that line were repaired in the afternoon, the restoration rate would rise to 87%.
On Wednesday, during the onslaught of storm Ernesto, up to 750,000 customers were without electricity, just over 50% of the consumer universe.
1 / 56 | In pictures: The effects of Tropical Storm Ernesto in Puerto Rico. Municipal officials in Canovanas tend to fallen vegetation caused by Tropical Storm Ernesto. – Ramon “Tonito” Zayas
Although Saca and other LUMA officials reiterated during the storm that it would be possible to estimate a period for the complete restoration of the system after 48 hours, on Friday they limited themselves to offering an estimate of 90%.
Alejandro Gonzalezdirector of Line Operations in the Central-South Region, said that restoring service to the last 10% of subscribers – approximately 150,000 homes or businesses – would be slower for various reasons.
“We have been through this for many years. Historically, when the system recovers and we exceed 90%, recovery begins to be slower because the remaining work takes more time and it is more difficult to access (the repair points). “We are seeing a faster recovery in terms of coordination, and the weather is a very important factor. If we maintain this climate, it will help us move forward a little more, but normally, those small areas that are left without service, it always takes a while,” Gonzalez reiterated, urging customers in those areas to maintain communication with LUMA.
No cost estimate
At the press conference, LUMA officials said that 880 “damage assessments” have been completed so far, based on aerial and ground inspections of the network. Juan Rodriguezvice president of Capital Programs of the company, however, said that It is difficult to estimate what percentage of the damage has already been identified..
As part of the inspections, LUMA has flown over 1,200 miles of transmission and distribution lines, Rodriguez said.
The engineer, however, was emphatic that assigning a cost to the infrastructure damage experienced is a separate process that has not yet begun.
“Our main goal right now is to restore customers. There will be a team that will go to work, take the reported damages, quantify them, do an engineering study and some designs – if necessary – and verify how much the estimate would be. We don’t have a preliminary number yet,” said Rodriguez.
Regarding health centers, LUMA’s Key Accounts Director, Melissa Pueyohe stated that, Among the health facilities, there are 92 that remain operating with electric generators and that are a priority for the company.Of those 92, 29 are hospitals, while the rest are diagnostic and treatment or dialysis centers.
Saca, meanwhile, said that LUMA had 90 of its approximately 300 substations out of service, but that 62 have already been restored, leaving 28 pending.