Hours before Puerto Rico feels the brunt of the Tropical Storm Ernesto, LUMA Energy The consortium on Tuesday maintained its brigades positioned in their “ordinary balance” at the regional level, with the expectation that the mobilization to the areas most affected by the cyclone will be a fairly simple process, said the coordinator of the regional operations centers of the consortium, Alejandro Gonzalez.
“We are maintaining the ordinary balance in each of the regions. We already have the six regions supplied with resources and materials. The reality is that, given the expectation of what is to come, for us, it is quite simple, once the atmospheric phenomenon passes, to mobilize personnel from one region to another. Because within these regions, 17 districts are divided, and they are not very far from each other,” stressed Gonzalez, also director of the transmission lines in the central-southern region.
LUMA currently has its regular staff of 1,196 active field workers, in addition to 230 employees from improvement and repair projects who have been reassigned to deal with foreseeable emergency situations. To prevent and respond to vegetation problems – which are expected to be the main cause of disruption during Ernesto – there are an additional 110 workers, for a total of 1,536 employees in the field.
As of 3 p.m. Tuesday, the number of customers without service stood at 19,404, one day after a breakdown in a transmission line – unrelated to the atmospheric event – interrupted the supply of more than 150,000 subscribers at a given time.
At this time, Gonzalez could not specify whether it would be necessary to import personnel from the LUMA headquarters in the United States, although he assured that it could be done in a short time.
“It was a lesson learned. The past taught us that it was good to have those agreements through parent companies, with external resources, outside of Puerto Rico, and that is already in place. If it is a major event, the agreements are activated and mobilization is worked on,” said the LUMA official, who also referred to other agreements with local contracting companies.
Asked about logistical adjustments for the mobilization of equipment – in the context of the controversial transfer of a transformer to the Santa Isabel substationwhich took several weeks and cost $4 million before it was discovered that the device was not working – Gonzalez stressed that LUMA has all the necessary contracts to carry out the different functions that may be necessary in response to the emergency.
“It is difficult to get ahead of ourselves, but I can tell you that the contracts are available,” he said in an interview with The New Day“It is a matter of activating them in case of a declared emergency.”
Attention to critical loads
Gonzalez, on the other hand, mentioned that LUMA maintains a registry of clients dependent on electrical equipment that exceeds 3,000 peoplealthough this is a dynamic figure. As with other facilities considered “critical loads” – such as hospitals and power plants – Water and Sewer Authority–, these consumers receive priority within the plans for restoring electrical service.
“We continue to invite customers to contact the number 1-844-888-5862 “so that they let us know and enter into the registration process. There are certain requirements to be met and it is handled with the confidentiality that it deserves,” said Gonzalez.
At a press conference earlier on Tuesday, LUMA President, Juan Sacaindicated that the consortium remains in communication with mayors to obtain information that facilitates the identification and registration of consumers with this type of needs.
Gonzalez also acknowledged that Ernesto could have an impact on ongoing reconstruction projects in the electrical system by delaying their execution.as well as on the components in need of repair whose work has not begun, as it is a “very weak (energy) system”.
“The complication with the vegetation system gives an important value to the issue of precipitation because the trees that are close to the lines gain weight and stick (to the cables). There is an important fact, which is the response time: while it is raining, it is difficult for us to work, it is difficult for us to access (the affected lines), and that represents a delay.“, Gonzalez stressed.
At the government press conference, the spokesman for Generate PR, Ivan Baezstated that, although the generating fleet maintains a capacity of close to 3,555 megawatts (MW) – sufficient to meet peaks close to 3,000 MW – it will be necessary to make adjustments in the operation of the 14 portable megagenerators acquired in March and located in the Palo Seco (Toa Baja) and San Juan plants. Specifically, Baez said that the barge that supplies natural gas will have to be removed for safety reasons, so the units will start to operate with diesel..
Baez, on the other hand, specified that Genera assigned personnel to the emergency generation units in Vieques and Culebra, which have the capacity to energize the island municipalities for approximately 12 days.