The executive director of the Central Office for Recovery, Reconstruction and Resilience (COR3), Manuel Laboysaid Tuesday that the changes that GeneraPR introduced to the project to purchase new rapid response units (“peaking units”) responded to an adjustment – notified in January 2023 – to the policies for approving funds by the Federal Emergency Management Agency (FEMA), but acknowledged that the increase in costs since then will limit the scope for carrying out other works.
Therefore, he warned that It is the company’s responsibility to expedite the procedures to avoid an even greater delay in the installation of the equipment..
According to Laboy, in January of last year, FEMA estimated the risk mitigation work that would be required in the country’s electrical infrastructure at $7.6 billion. In making a global estimate of the cost of the work, the federal agency indicated that the projects could be financed, indistinctly, under the sections 404 or 406 of the federal Stafford Actwhich provide, precisely, for work that reduces risks from future natural phenomena, the official explained.
Upon notification, COR3, together with the Electric Power Authority (AEE), GeneraPR and LUMA Energyopted to move most projects formulated under section 404 – such as the peak units – to section 406, to maintain greater flexibility for reconstruction work in other sectors. By federal provision, the allocation of funds under 404 faces a cap of $4 billion among all sub-recipient agencies, of which 75% comes from FEMA and the remaining match from the Community Development Block Grant in Disaster Relief (CDBG-DR).
Under 406, “there is more budget, in general, and we can absorb cost increases”highlighted the head of COR3.
“Under 404, absorbing those increases is limited, because I have other mitigation projects, (such as those) of the municipalities, those of the (Aqueduct and Sewer Authority), everyone. In 406, I have $7.6 billion – a much larger budget – for the electrical system,” Laboy added in an interview with The New Day.
The mitigation funds available to address grid needs are in addition to the $10.5 billion authorized by FEMA in September 2020.
Faced with this scenario, GeneraPR, after assuming control of the country’s generating fleet in July 2023, modified the process that AEE had initiated to purchase 11 “peaking units”, which are the smallest generating units in the system and are activated when peaks in electrical demand occur or when the main plants fail, with the aim of mitigating load shifts.
Although, at that time, the operator projected that –after the changes to the process– could award the request for proposals (RFP) by December 2023at a cost of close to $800 million, and have the units in operation by the end of 2025, in a recent motion to the Puerto Rico Energy Bureau (NEPR) reported that the new estimated cost amounts to $911 million and that the machines would be operational in 2027, according to This newspaper reported on Monday.
“
This increase in the number of ‘peakers’ is eating up more of the budget, because it is finite. This puts us in a position to see what other projects may be affected. ”Manuel Laboy, Executive Director of COR3
Under the PREPA RFP, which was due to be awarded in the summer of 2023 – coinciding with the transition to GeneraPR – the rapid response units would have begun operating in mid-2025.
“I think that, based on the parameters that were included in the PREPA RFP, under those assumptions, such as specifications and mitigation strategies, it was a reasonable expectation. There is always a risk, under PREPA or anyone else, that it will be delayed due to external factors. In the case of Genera, they decided, and consulted with the NEPR, on some changes to the bidding strategy and certain technical aspects to the equipment specifications. By making a change, that alters the timeline.“Laboy accepted.
In terms of execution, he said that, in the meetings he has held, “both internally with Genera and FEMA, as well as with the federal Secretary of Energy (Jennifer Granholm), they have been reminded of the importance of speeding up these processes.”
“The changes that occurred due to the bidding strategy and technical aspects are understood (…), but It has been emphasized that there is a need, and you have been told, to speed up the bidding, contracting and purchase order processes.“The engineer added, emphasizing that both GeneraPR and LUMA Energy have access to capital to advance design work and purchase equipment before FEMA commits funds to a particular project.
The official also acknowledged that, if the increase in costs predicted by GeneraPR materializes, The AEE would have to disburse around $11 million additional corresponding to the 10% matchingwhile the amount available under the AEE 406 funds would be reduced.
“This increase in the number of ‘peakers’ is eating up more of the budget, because it is finite. That puts us in a position to see what other projects may be affected,” said Laboy, pointing out that the Fiscal Oversight Board is aware of the importance of approving sufficient funds for state matching.
The director of COR3 described the acquisition of the “peakers” as one of the four most important projects for the medium-term reliability of the energy system, along with the installation of storage batteries, the clearing of vegetation from the power lines and the acquisition of temporary generators.