The selective blackouts that have left hundreds of thousands of customers without power repeatedly throughout this week will, in all likelihood, extend for the next few days, the spokesman for the company acknowledged. Generate PR, Ivan Baezin the face of simultaneous breakdowns in multiple generating plants.
Of the three main units of the Genera PR fleet that have suffered forced departures in recent days, The #2 of the Aguirre plant (Salinas) would be the first to return to service, which would occur between this Saturday and SundayBaez said. The unit, however, would come into operation with a limited capacity compared to the 450 megawatts (MW) that it can nominally produce.
For Friday night, LUMA Energy estimates that it will face a deficit of 435 MW with respect to demand.
On Thursday, nearly 250,000 customers – about 15% of consumers – suffered overnight load shedding as a result of power plant outages.
At the moment, Genera PR also has units #6 of Costa Sur (Guayanilla) and #6 of the San Juan plant out of service, while the cogeneration plant EcoElectric (Penuelas) is operating at half capacity due to the forced shutdown of one of its two gas turbines, with no estimated date for its return.
“The latest update we have with the fault in Costa Sur, we understand that this unit (#6) will be able to enter into service next Thursday. The expansion joints, which had not been changed for 20 years, were obtained and it broke down. We have the spare parts, and we are in the process of exchanging them.“Baez said about the machine with the capacity to generate over 400 MW.
In the case of unit #6 of the San Juan plant, which also broke down after the Tropical Storm ErnestoBaez said he does not have an estimated return date.
“At San Juan #6, the assessment is being done. It will take more time there,” the spokesman admitted.
“
This has been quite a domino effect after several months of relative calm and the system operating well. ”Ivan Baez, spokesperson for Genera PR
EcoElectrica, meanwhile, does not have an estimated date for returning its unit #1 to service. That unit was forced out of service early Thursday morning, an incident that, the cogenerator noted, “coincided with other events in the electrical grid, as reported by the operators of the electrical system,” in reference to LUMA Energy.
“Until the investigation process is complete, we will not be able to say whether these events are related.”the company said in writing.
“This has been a domino effect after several months of relative calm and the system operating well. But, after Ernesto, we had this whole series of events. The important thing is to try to repair them, put them back into service as soon as possible and restore the generation capacity. I would wait for Aguirre #2 to come in before making a positive prediction, because, at this point, I remain conservative with the forecast. “We have a scenario similar to yesterday’s today (Friday),” said Baez.