The Department of Natural and Environmental Resources (DRNA) and the Autonomous Municipality of Salinas filed a lawsuit to request the demolition of the structures allegedly built without the proper permits on a lot in the Las Mareas neighborhood, south of the Camino del Indio, in said town. .
In the legal appeal – submitted to the Court of First Instance of Guayama – both agencies also request that a use permit that would have been issued without jurisdiction be revoked and that the stoppage of that use, as well as the construction works, be ordered. construction.
The lawsuit cites a determination of the Planning Board (JP), which indicates that the permit was issued contrary to the law because “the parcel of land where the project linked to the permit is located is declared as a natural reserve under federal and state administration and regulation.”
The fragment that includes the legal appeal on the JP’s decision – which was ratified by the appellate and Supreme forum – reads that “the entire property of the land where the property tied to the permit under audit is located is located in an area delimited as coastal barrier”. Additionally, 98% are in the resource preservation district, which “comprises properties or parts thereof, and whose existing natural order must be maintained to a maximum.”
“The DRNA claims to be the owner of the properties occupied by third parties and requests that the court declare its ownership and order the eviction of the defendants,” the appeal adds.
The defendants are Miguel Flores Torresowner of a construction project on the site, and the engineer Angel Rodriguez Sanchezthe licensed professional who issued the permit.
In the discovery of evidence, it came to light that Torres Flores “began construction on the property he occupies without obtaining a permit and that he was advised by engineer Rodriguez that the permit could not be obtained because ‘it was too close to the water’” .
Regarding the demolition, the DRNA and the city council demand that the court order that the work be completed “within a reasonable period, not exceeding 60 days.” In the event that Flores Torres fails to comply with the term, the plaintiffs request that “the demolition can be carried out by the municipality of Salinas, subject to Flores Torres reimbursing the expenses incurred by the municipality.”
The secretary of the DRNA, Anais Rodriguez Vegaexpressed in written statements that, “By advancing this fight against violations of environmental laws and regulations through appropriate procedures, we are sending a strong message that we will no longer tolerate them”.