Ensure compliance with agreement recently reached with the federal government and give way to the complex closure works of the municipal landfill of Toa Alta – a project that will take “many years” – will require an estimated investment of $13 million that is still in the approval process, he indicated Carlos Lopez Freyteslegal advisor to the city council.
“Reaching an agreement helps us focus the closing process on the technical part and complete the legal part of a judicial process. With these agreements, we are now clear about the direction that will be finally executed to achieve the closure plan that needs to be carried out for the landfill.”emphasized Lopez Freytes, the mayor’s lawyer. Clemente “Chito” August.
The agreement, which must still be validated by the federal judge Silvia Carreno Coll and go through a period of 30 days of public comments to come into force, is the product of the process that began with a lawsuit United States Department of Justice against the Municipality, in 2021, after the Federal Environmental Protection Agency (EPA, in English) identified failures in the operation of the landfill that placed the environment and the surrounding communities due, among other elements, to the poor management of leachate generated by accumulated garbage.
The draft of the closure plan, Lopez Freytes commented, is in the hands of the Department of Natural and Environmental Resources, agency with the responsibility of evaluating and approving the document. He specified that, once an approved plan is available, the Municipality would proceed with the work of designing the plans to carry out the works that entail a landfill closure.
“
We are already clear about the direction that will be executed finally to achieve the closure plan that needs to be carried out for the landfill. ”Carlos Lopez Freytes, legal advisor of the Municipality of Toa Alta
In a closure plan, “it is adequately identified how runoff water or leachate is going to be managed, how the landfill is going to be prepared to waterproof the areas so that less leachate is produced (and) how gases are going to be controlled.” , among multiple other measures that must be done,” said the former president of the disappeared Environmental Quality Board.
“We are talking about a process that takes many years to complete and execute. That’s why it’s so expensive.”he pointed out.
In recent months, the Municipality resorted to funds from the American Rescue Plan Act (ARPA) to carry out work with which it had failed to comply according to a preliminary agreement with the EPA and federal Justice, but, at the moment, there are conversations with the Housing Department to allocate Community Development Block Grant mitigation funds that allow the works to continue and direct the closure of the facility, which has not received waste for two years.
“What we have been discussing with the central government, for the purposes of estimating the closing cost, is that it may exceed $13 million.”said Lopez Freytes.
Last July, The new day reported that, in motions before the Federal Court of San JuanJustice had stated that the Municipality was failing to comply with several provisions of the preliminary agreement signed in August 2022. Monday’s agreement, precisely, included the payment of a penalty of $50,000.
Among other things, that agreement – which remains in force – stipulates that an intermediate cover had to be applied to the landfill, at the rate of one acre per month for the first year and two acres per month starting in the second year, until covering the 34 acres of the landfill. facility. Likewise, the Municipality of Toa Alta had the obligation to request from the Water and sewage Authority (AAA) permits for the disposal of leachate in a treatment plant.
“In order to carry out these tasks, the Municipality needed to be given an allocation of funds, and the process of allocating the funds has been delayed”said Lopez Freytes, pointing out that it was then that it was decided to resort to the ARPA funds that the central government had allocated to Toa Alta to “begin the process.”
Since then, the Municipality has managed to apply the intermediate cover to approximately five acres and began the procedures with the AAA to define how the leachate will be disposed of, he noted. Monday’s agreement with the federal government details that Landfill Technologiesthe company that operated the landfill until 2022, must complete the tests of the leachate pumping system and then transfer that function to the Municipality.
From the minutes of a status hearing on January 25, it appears that the federal Justice lawyers told Judge Carreno Coll that, once the public comment period on the agreement was completed, By March, the so-called consent order would be presented to the court that would cement the stipulations between the parties.