If he Puerto Rico Energy Bureau (NEPR) gives way to the requested amendments to the contract of AES Puerto Rico to produce energy by burning coal, the impact, charged to consumers’ pockets, will approach $45 million throughout 2024, according to the document made public on Friday by the Electric Power Authority (AEE).
The proposed amendments contemplate an initial payment to AES of $5,241,441, under the premise that the contractual adjustment would take effect on or before January 1. “Additional changes would be necessary based on the final effective date of the Third Amendment”indicates a footnote in the proposal presented to the NEPR.
In addition to the advance payment, the clauses contained in the draft provide that, between January and November 2024, AES receives a monthly payment of $8 for each kilowatt of “dependable capacity.” With its capacity of 454 megawatts – equivalent to 454,000 kilowatts – between the two AES generating units, The amount of the charge would be around $3,632,000 per month for that period. The reliable capacity charge would then be reduced to $1.75 per kilowatt of capacity starting in December.
The increase in payments corresponds to the proposed “Green Transition Stabilization Payment” which, in principle, would allow AES to replace its energy with clean fonts after 2027, when its contract concludes and the statutory ban on the use of coal to produce electricity in the country comes into force.
“These documents, which are made available by order of the NEPR, basically, confirm the order established by the NEPR of an increase in consumer bills of $15 million quarterly, to satisfy a debt of between $40 (million) and $45 million. As I mentioned before, Shocking consumers should be the last option, especially when it comes to a private generator.”stressed the consumer representative before the PREPA Governing Board, Tomas Torres Placainsisting that, if the economic capacity of AES is demonstrated, no additional charge should be guaranteed to subscribers.
When approving the rate adjustment that will apply to customers between January and March, the NEPR included a charge of 0.44 cents per kWh as a contingency in case it endorses AES’s contractual amendment. In the resolution, the entity specified that The calculation for the surcharge is based on the potential need to collect $15,247,171.65 in that period, which would include the advance payment of more than $5 million to the cogenerator.
Transition payments or operational costs?
Although the increase in payments to AES would be intended to give way to the transition of energy sources, the NEPR questioned, in a resolution of December 22, that the main justifications of PREPA and the private company seem to revolve around increases in operational costs as a result of the obligation to export the coal combustion waste (CCR, in English). In the contractual amendments, it is stated that, as of the Law 5-2020any commercial use of the CCR was prohibited, a possibility that had been included in 2015 in the agreement between the government and AES.
“The position, as expressed in the documents, is that it is not justified to increase the payment to AES for something that they contracted that they were going to attend to, and that is part of their business. As we mentioned in the comments, why is AES paying to dispose of the ashes in a landfill in the United States? If they claim that ashes are a beneficial product, why don’t they sell them? (The export of the ashes) is something that they assumed as a business risk,” said the environmental lawyer. Ruth Santiagoalluding to the original version of the AES and PREPA pact – which dates back to 1994 –, which ordered the disposal of the ashes outside the country.
Although the PREPA finally agreed to publish the requested amendment in its entirety, the member of the Environmental Justice Advisory Council White House He maintained that there are still loose ends, among which he mentioned an alleged incentive of $72 million that would go to AES to begin your transition to solar energyand which emerged in a meeting on November 21 between the NEPR and company officials and PREPA, the recording of which was later released.
Preliminary terms disclosed
Included in the amendment’s annexes are preliminary terms of the renewable energy project that would replace the coal plant in the coming years. AES, according to the document, would commit to building about 300 megawatts of capacity in photovoltaic energy or storage batteries, that would be located in the same facilities as the coal plant, in Guayamaor in some other property agreed upon with PREPA.
According to the annex, the negotiations of the commercial terms of the pact – which would have a validity of at least 25 years– should be completed by December 31, 2025.
The projects, it is specified, would be additional to those already carried out Clean Flexible Energya subsidiary of AES, following the first “tranche” conducted by the NEPR, and which must begin producing energy by the end of 2025.
Separately, Santiago and Torres Placa warned that Any new project must guarantee better energy purchase costs than those approved by the NEPR as part of the first round of procurement, which fluctuate between 10 and 15 cents per kWh. The consumer representative also rejected that AES can negotiate additional contracts without going through a process open to other bidders.
“In Puerto Rico, there are excessively high electricity costs, which may increase with PREPA’s Fourth Amended Adjustment Plan submitted (on Friday) by the Fiscal Oversight Board (JSF), which proposes an increase to the legacy position,” stressed Torres Placa.