Repair of a pipe Aqueduct and Sewer Authority (AAA) drilled by the contractor who carried out the earth excavation for the installation of the post for the controversial advertising billboard in front of a residence in the urbanization New Porthad a cost that amounted to $16,430.
Now, the AAA is preparing the invoice that it will send to the company CM Group LLC, owner of the facility, after confirming that the private entity does not solicitous authorization to the AAA to carry out said excavation, an essential process, as it allows the AAA to evaluate and notify the proponent about the pipes in the area and precisely avoid breaks.
“The investigation was carried out by our Excavation Center and no request was found in relation to the work,” said this Sunday the director of the AAA metro region, engineer Roberto Martinezin written statements to The New Day.
The break in the drinking water pipe, which measures six inches in diameter, was reported last Tuesday, the same day that Pro-Steel Services Corp. excavation work for the installation began. The situation caused the interruption in the drinking water service of 50 families. Martinez indicated that the amount of water lost due to the break could not be measured.
Although it was not until last week that the case became public, the saga of the controversial billboard has its origins four years ago, when CM Group LLC began proceedings before the Permit Management Office (OGPe) and the Municipality of San Juan to rehabilitate the home, with the purpose of converting it into a “specialized accommodation”, as spaces that house people with a physical, emotional or mental disability are called while they receive treatment.
After obtaining the use permit for that purpose, the application was submitted to the Municipality to build the billboard, in front of the residence, property of Hector Morales Vargasformer secretary general and electoral commissioner of the New Progressive Partyand former president of the Planning Board.
In the middle of two permit processes that were running at the same time, the OGPe archived, on November 25, 2021, the permit to use the accommodation after failing to correct the fire prevention certification, and authorized the November 15, 2022, a amended construction permit valid for two years for the installation of the billboard. The residence, meanwhile, has been marketed on the Airbnb platform as a property available for short-term rental, under the name “Casa Florecer.”
On Tuesday, the same day the breakdown was reported to the AAA, the Municipality of San Juan fined the company a sum of $13,000. Pro-Steel Services Corp. for not having the required permits to close the streets and make way for construction, the mayor’s office confirmed. However, on the same day, the municipal administration allowed the contractor to continue with the work. When questioned by this means, the mayor Miguel Romero indicated that the company was operating with a “valid (construction) permit.”
“As they had a valid permit until then, it is not until they break a water pipe that this whole situation comes out and is responsibly investigated and, when investigated, which clearly seems illegal to us, we went to revoke it”said.
The permit for the street closure was issued last Tuesday and provides that CM Group could only extend the construction work until tomorrow, Monday. At the same time, the Municipality of San Juan appealed, on Friday, to the Court of First Instance with an appeal to revoke the construction permit and order the demolition of the structure in the middle of a residential area.
Stay tuned to www.elnuevodia.com for an update.