The power outages Due to a generation deficit, they will most likely extend until this weekend, given the unavailability of three of the base units in the hands of GeneraPR and all the production of the cogeneration plant EcoElectricwhose plants are receiving scheduled maintenance.
“I think that, in the short term, until the end of the week, we will be seeing moments of challenges due to insufficient generation due to repairs in several of our units, and our colleagues at EcoElectrica are also carrying out work.”he expressed Ivan Baezspokesperson for GeneraPR.
On Wednesday, at 5:30 pm, LUMA Energy projected a deficit of 133 megawatts (MW) to meet the demand anticipated for the nighttime schedule.
At the moment, GeneraPR has out of service units #6 of the San Juan plant, #2 of Aguirre (Salinas) and #4 of Palo Seco (Toa Baja), which together have a capacity of close to 900 MW. Unit #2 of Aguirre would be returning to service in October, while #6 of San Juan will have to wait until January 2025 and #4 of Palo Seco, until summer of next year, as Baez had previously indicated.
Meanwhile, the three EcoElectrica units (Penuelas) contribute around 540 MW to the system. The spokesperson for the cogenerator, Yamaris Alancastrosaid that the annual maintenance of the plant, originally scheduled for March, had been postponed on multiple occasions.
The work, which will continue until this weekend, “will allow the plant to continue operating reliably and contributing to Puerto Rico’s electrical system.”Alancastro added, in writing.
Exchange of signs
Meanwhile, Baez stressed that, although the breakdowns in the generating fleet “are the responsibility of Genera”, the company considers that it is no coincidence that the damages in Aguirre #2 and San Juan #6 occurred in the days following the Tropical Storm Ernestowhen LUMA allegedly requested that generation be limited in view of the volume of customers who remained without service due to problems with the electrical transmission and distribution system.
“Whenever you have a reduction in demand, you have to reduce the load on the system to avoid a collapse, such as a general blackout. Our units and our cogeneration colleagues did the same. Our units, indeed, began to suffer various types of damage two days after (Ernesto)“Baez said, noting that GeneraPR raised the issue on Tuesday during a Senate hearing.
In response, LUMA issued a written statement stressing that “the most recent generation problems, including load shedding related to generator breakdowns, have been caused by insufficient generation or by problems in the obsolete generation plants that Genera currently operates.”
“It is important to clarify that, at LUMA, we are not responsible for generation, we do not manage or operate it. Nor are we responsible for the state of the generation facilities. Genera is and must accept its responsibility when its plants fail.“the company added.
Wide impact
Since early Wednesday, however, tens of thousands of customers have suffered interruptions due to failures in transmission and distribution lines. In Bayamon, for example, A dozen public schools had to suspend classes due to the lack of electricity and, in some cases, drinking water.
“In the 12 schools without electricity and drinking water, we are implementing schedules, taking advantage of and trying to make the most of the teaching time to ensure compliance with contact hours. We are working asynchronously, with homework,” said the regional superintendent. Duhamel Adames Rodriguez regarding the facilities located in Bayamon, Toa Baja, Toa Alta and Corozal affected by the failure in transmission line 37400, which left over 60,000 subscribers without service.
Meanwhile, in Jayuyathe mayor Jorge Gonzalez Otero He regretted that, after the power service was restored on Tuesday night –albeit with low voltage problems–, on Wednesday a transmission line coming from Utuado tripped again, causing another general blackout in the municipality.
“Once again, we are 100% without service. They disconnected again to supposedly fix the fault”the municipal executive commented to The New Dayaround 1:00 pm
Keila Lopez Alicea contributed to this story.