The Aqueduct and Sewer Authority (AAA) maintains the expectation of completing the repair of the 72-inch line of the Superacueduct on Monday, in Bayamonafter a third leak was identified during the early hours of this Saturday that could add about 12 hours of work.
The executive president of the public corporation, the engineer Luis Gonzalez Delgadoindicated that during the early morning work another leak was detected at a point further down the line.
The official maintained that, if the third leak had not occurred, they would have been able to finish the work on Sunday. However, he assured that the expectation is to complete the repair work on Monday, as long as no other problem occurs.
“Our expectation continues to be to finish by Monday, if there is no further inconvenience”he stated. “We are already working to access the last fault that we identified today and basically that is what could add an additional 12 hours of work”he explained.
Gonzalez Delgado added that the failures are concentrated in the joints of the pipeline, which is located in a section with an approximate inclination of 30 degrees.
1 / 28 | In images: this is how the new repair of the Superaqueduct takes place. Sectors of San Juan, Bayamon, Guaynabo, Loiza, Caguas, Gurabo, Juncos and Aguas Buenas could experience from intermittencies to interruptions in the drinking water service during repair work for a breakdown in a 72-inch diameter line of the Superaqueduct. – Carlos Rivera Giusti/Staff
The executive president of the AAA explained that the breakdowns to the line could have occurred during a displacement caused by water escaping from the leaks.
He assured that one of the joints has already been repaired and that AAA brigades are working to move the scaffolding and continue with the other necessary repairs. The public corporation does not contemplate, at the moment, rationing of the drinking water service.
Gonzalez Delgado estimated that more than 50% of affected customers could have service within the first 24 hours after the system opened, scheduled for Monday.
“Unlike the event we had in October with the breakage of the Superaqueduct in Manati, this time the plant has not stopped operating. We don’t have to build a plant to start distributing, we have the system full. “It is a matter of beginning to open the valves and for the water to flow from the last reserve tank to the municipalities.”he emphasized.
The cost of the repair, not including hauling water or other expenses related to the emergency, is estimated between $300,000 and $500,000, the official indicated.
This calculation does not include the purchase and distribution of water, the establishment of shifts for the oases, nor the costs associated with AAA staff who maintain open plants and participate in multiple work shifts.
Emergency order and mitigation measures
For her part, the governor Jennifer Gonzalez Colonwho arrived on Saturday in the area where the work is being carried out, indicated that the government operates under a current emergency order, which has allowed work to be accelerated and resources to be coordinated to address the situation.
“We are operating with an emergency order in force”said the president, pointing out that this tool has also allowed work to be carried out at the Sergio Cuevas plant, where there is an investment of $176 million for maintenance and/or repair work.
He reported that, as part of the efforts, he coordinated with the National guardhe Housing Departmentthe Public Housing Administration (AVP) and other agencies to distribute water in affected communities.
Gonzalez added that he spoke with the director of the Tourism Company (CTPR) and with the president of the Hotel Association, Clarisa Jimenezdue to concern about the impact of the breakdown on hotels and hospitals.
According to Gonzalez, stations will be designated that will operate 24 hours a day so that hotels and hospitals can supply themselves with water, due to the volume of transport required.
The president also announced that, on the recommendation of the engineer Carlos Pesqueraa corrosion study will be commissioned for the Superaqueduct, whose construction is turning 30 years old.
Likewise, he stated that the replacement of the valve system in the metropolitan area should be studied. so that it can be managed more digitally and not manually, with the aim of reducing constant manipulation of the valves.
Assistance to residential, shelters and care homes
For her part, the secretary of the State Department Rosachely Rivera Santanawho accompanied Gonzalez, indicated that Housing was at the residential Luis Llorens Torreswhile government personnel went to the residential Nemesio Canales to meet the needs of residents affected by the lack of water.
Rivera Santana pointed out that he also coordinated with the Fire Department Bureau to use trucks that could supply water to residences located on second, third and fourth floors. In addition, he said that tanker trucks were coordinated with the National Guard for Puerta de Tierra and other affected residences.
For her part, the secretary of the Family Department, Suzanne Roig Fuertesreported that agency personnel have visited communities with a high population of older adults, bedridden people or residents with particular needs, who have also been supplied with bottled water.
Previously identified breaks
The original fault was identified in a section of the Superaqueduct that runs through a rural area of Bayamon, after the AAA detected levels outside the norm in its tanks, particularly in the Toa Baja reserve tank.
1/12 | Superaqueduct: this is how the megapipeline was built at a cost of $585 million. The idea for the project arose from engineer Antonio Santiago Vazquez, in the 1980s, under the administration of Carlos Romero Barcelo. Then, his idea did not prosper, but it was revived, a decade later, by Pedro Rossello. In the photo, Santiago Vazquez, considered “the father of the Superaqueduct,” stamps his signature on the pipe, when construction was announced in 1996. – TITO GUZMAN
Gonzalez Delgado explained that personnel from the AAA and the company that manages the Superaqueduct began to review the nearly 40-mile line, which extends from Arecibo to the municipality of Bayamon, to validate if there was any failure.
The official maintained that the original breakdown was located, using drones, with the support of the Municipality of Bayamon. Once the leak was identified, teams moved to the area to begin excavation and repair work.
Subsequently, in an update provided on Friday, the AAA CEO confirmed that, During the work to address the first break, the staff identified a second point of interest on the Superaqueduct line.
That second discovery led the public corporation to extend the estimated completion of the work until Monday, before this Saturday a third leak was identified in the same pipe.
1 / 6 | DACO carries out operations in supermarkets after freezing water prices. Consumers come to Plaza Loiza in search of bottled water due to the lack of water in several municipalities in the metropolitan area. – Xavier Araujo