Wait for demolition of the illegal wall in Sol y Playa will be extended until next week

Wait for demolition of the illegal wall in Sol y Playa will be extended until next week

The demolition of the illegally built wall in front of the Sun and Beach condominiumin Cornerwill be delayed, at least, until next week, because the environmental mitigation and safety tasks that the contractor must implement have not been completed.

“As in any construction project, environmental protection measures are taken first and safety measures must also be worked on.”. That takes a while. We hope that, in the coming days, the demolition work will begin, once the contractor makes sure that all the measures are taken appropriately,” the engineer indicated this Thursday. Emilio Colon Zavalaproject manager.

According to Colon Zavala, it is “highly probable” that the demolition phase could start early next week.

The president of Camp Carey, Laura Nazariodenounced, however, that, during the work this Thursday, the labeling of the different areas corresponding to the project was not completed, despite the fact that, supposedly, the condominium owners had been notified that this work would progress over time. throughout the day.

“It remains exactly the same,” said the leader of the environmental organization. “They can’t start until everything is labeled. If it is not labeled today, even if it were labeled tomorrow, other things would still be missing (prior to the demolition)”added the lawyer.

Nazario added that, previously, a security guard Department of Natural and Environmental Resources (DRNA) informed him that, “if everything went well,” the demolition would begin on Monday.

Throughout this week, Camp Carey, the Council of Sun and Beach Owners and the DRNA engaged in an exchange of motions before the Aguadilla Courtin which the condominium demanded that the protesters remove the tents that they have established on the street that gives access to the Los Almendros beach. Camp Carey, meanwhile, responded by asking the judge Abid Quinones to carry out a visual inspection in the area where works aimed at the demolition of the wall that was illegally erected two years ago have just begun.

According to the legal representation of the residents, Camp Carey has hindered the initial phase of the work, preventing machinery from accessing the area where the remnants of the wall are located.

“Control of the property, or land of the project, belongs to the contractor. For this reason, there is an authorization for the use of a public domain asset. Obviously, the contractor keeps his equipment on private property, as he is doing, with measures to minimize contamination,” emphasized Colon Zavala.

The Carey Camp has rejected that its tents, located on the road that gives access to the condominium and the beach, block the passage of pedestrians or vehicles, while pointing out that the delay in the work responds to non-compliance with the pollution control plan. erosion and sedimentation by the contractor. In that sense, they pointed out that last Monday, when the machinery was transported to the area with a view to beginning the demolition the next day, “it was observed that one of the machines was dumping or ‘leaking’ oil.”

The DRNA, meanwhile, aligned itself with the claims of the environmental group and censured the condominium’s alleged attempt to “eliminate a citizenry on guard and protector of natural and environmental resources that has been present when the DRNA has not had a physical presence, activating with this immediate action to address a violation of law or prevent it.”

Kumneger Media