The Energy Czar, Joshua Columbusanticipated that Unit 6 of the Costa Sur plant, in Guayanilla, could be synchronized again to the electrical system “at some point” this Friday, while It is still being investigated what happened in the switch yard where the “condition” that caused his abrupt departure was detected.
In an interview with WKAQ-580, Colon explained that this transmission center, where the unit’s generation comes out through 230 kilovolt (kv) lines, is under the jurisdiction of the consortium. LUMA Energy.
According to the tsar, Unit 6 was generating about 340 megawatts (MW) when its protection system detected a “condition” in that switch yard and took it out of service at 8:26 pm on Thursday.
1 / 14 | What is LUMA Energy’s strategy to reduce light interruptions caused by animals? Puerto Rico, with its high vegetation and abundant wildlife, faces a constant challenge: service interruptions that affect thousands of customers when animals come into contact with energized equipment in substations and transmission lines. – Xavier Araujo
The event caused a second blackout that, at its peak, affected over 190,000 subscribers.
The official indicated that, as soon as the unit left, technical personnel from the two private companies in charge of the electrical system were dispatched: Generate PRresponsible for the operation of the plant, and LUMA Energy, operator of the transmission and distribution network.
According to Colon, Genera PR personnel inspected the plant and, Until now, he had not identified any situation within the facilities or Unit 6 itself that would have caused his departure.
Meanwhile, LUMA Energy employees went to the switch yard to carry out the corresponding inspections and determine if any conditions remained that would prevent operations from normalizing.
“So far they have not reported that they have found any permanent situation on any of the lines that leave that center,” said Colon.
The Energy Czar explained that several 230 kV lines leave from that yard that transport electricity to different points in Puerto Rico.
Among them he mentioned line 50400, which heads towards the western area; 51200, towards Cambalache; the 502, towards Manati; and 50300, towards the Aguirre area.
1 / 15 | Exclusive access: dredging advances in Las Mareas de Guayama bay. Dredging of Las Mareas Bay, in Guayama, began on June 21 and is 47% ready. – Ramon “Tonito” Zayas
For his part, the spokesperson for LUMA Energy, Hugo Sorrentiniconfirmed to The New Day that the company was continuing to investigate what happened, but that so far it had not identified damage to the lines or the equipment in the switch yard.
“We haven’t identified anything yet. We continue to investigate, but so far nothing has been found,” Sorrentini indicated.
The spokesperson added that the lines leaving the transmission center remained in service and that specialized substation personnel continued to inspect the equipment.
Sorrentini explained that the switch yard is a substation to which several units of the system are connected and not exclusively Unit 6. He added that the plant EcoElectrica It also shares that facility, so two generating plants converge there.
The Energy Czar maintained that if inspections did not reveal permanent damage or any condition that would compromise operations, Genera PR could synchronize Unit 6 again on Friday. However, he did not offer a specific time for his return to the system.
The New Day He attempted to get an update from Genera PR about the drive’s boot process and when it could sync, but did not immediately receive a response.
According to Colon, all customers affected by the second event recovered service around 12:00 am on Friday. The official highlighted that the departure of Unit 6 occurred after the period of greatest energy demand on Thursday had concluded.
This blackout was the second caused on Thursday by the departure of a Costa Sur unit.
Around 1:00 pm, Unit 5 went out of service due to a breakdown in one of its boilers, which caused a “disturbance” that left over 130,000 subscribers without electricity.
Colon explained that this first event could be corrected in a period of between 30 and 45 minutes because, at the time of the breakdown, the system had reserve generation available.